My last
post was the first of at least three or four dealing with interesting
things I learned from the presentation
by Felek Abbas of NERC and Lew Folkerth of RF at RF’s CIP compliance workshop
last month in Baltimore (the download includes all of the presentations at the
workshop. Felek and Lew’s presentation starts on slide 19).
Felek’s part
of the presentation started with a discussion of compliance dates for the Low
impact requirements in version 6. Since those should be well known to you
already, I won’t discuss them now. What I found interesting was slide 29, which
says in part:
- CIP-003-7 was filed with FERC on March 3, 2017
- However, CIP-003-7 is very unlikely to come into effect
before September 1, 2018. You will need to comply with the CIP-003-6 version
of these requirements beginning September 1, 2018, until the effective
date of CIP-003-7.
This was
interesting because, in the whole LERC discussion last year, it had never even
occurred to me that CIP-003-7 wouldn’t be in place by 9/1/18; I never thought
there would be a serious possibility that entities would have to comply with version
6 of this standard, and then version 7 (as I’ll discuss below, having to do
both doesn’t change what you have to do to comply, but it certainly does change
the language you need to use to document compliance). However, this was
probably because I hadn’t bothered to read the implementation
plan that got passed with CIP-003-7(i) this year.
When I read
the plan after hearing Felek’s discussion, I realized that the words “very
unlikely” on the slide should have been replaced with “mathematically
impossible”. This is because the plan says “…Reliability Standard CIP-003- 7(i)
shall become effective on the first day of the first calendar quarter that is
eighteen (18) calendar months after the effective date of the applicable
governmental authority’s order approving the standard…”
So let’s do
the math. CIP-003-7(i) was filed with FERC on March 3. If FERC had approved it that day (which I doubt has ever
happened for a NERC standard, or almost anything else), the effective date
would have been October 1, not September 1, 2018. Of course, I doubt this would
have been a big deal, since the Regional Entities wouldn’t have issued any PNCs
(the successor of PVs) for turning in V7 documentation during the month of
September, 2018. And even if FERC had taken just 3-6 months, I think the Regions
would still follow the same approach.
However, unless
you’ve been living in a cave in the Himalayas for the past year, you have
probably heard that there is a new administration in Washington and they have
been very slow to make high-level appointments to almost any Federal agency. In
FERC’s case, this situation was made worse by the fact that a key resignation
in January left the Commission with only two Commissioners (out of a normal
five), meaning they don’t have a quorum to conduct business.
And since
one of the remaining commissioners has announced her intention to resign, two
more new Commissioners need to be appointed and confirmed by the Senate, then
get comfortable in their new jobs, before there is any chance at all that
CIP-003-7(i) will be approved. So it’s almost certain now that it will be
summer 2019 at the earliest before the new standard comes into effect, and that
there will be a period of at least nine months during which entities will have
to comply with CIP-003-6 (and when I’m talking about CIP-003 v6 or v7, I’m
specifically talking about Section 3.1 of Attachment 1 of CIP-003. The single
sentence in this section is the only substantial change between the two versions).
However, as
I implied above, this shouldn’t require entities to implement procedures or
technologies to comply with CIP-003-6, then rip them out when CIP-003-7 finally
comes into play. As I discussed in this
post last November, almost everything – with one exception that I’ll discuss
below – that you could do to comply with Section 3.1 of Attachment 1 of
CIP-003-6 will still work under CIP-003-7.
The one
exception to this statement is if you had had your heart set on the fact that
there is a routable-to-serial protocol conversion within say a substation, as
reason why you don’t have to take any more protections on the routable
connection to the substation. I believe this was the one case that FERC had in
mind when they ordered NERC to eliminate the word “direct” from the LERC definition,
when they approved CIP v6 in Order 822.
So don’t plan on being found compliant if you do this.
Given that
practically everything else you can do to comply with CIP-003-6 will work for
CIP-003-7 as well, this means that the only difference will be your
documentation. But you definitely can’t use the same words to describe the same
setup in both versions. For one thing, you need to lose the word LERC. It
sleeps with the fishes. If you’re looking for clues on how to do the v7
documentation, you might look at the post from last November, referenced two
paragraphs above.
The views and opinions expressed here are my own and don’t
necessarily represent the views or opinions of Deloitte.
No comments:
Post a Comment